Start free

Prep plan and defrosting

The “runs out by 7 pm” alert, the kitchen production plan, prep for dated orders, the defrost list and a supplier order draft

6 min read Open this screen in the demo
On this page 12

Prep plan, defrosting and purchasing for the shift

Check what will run short during the shift, hand the plan to the kitchen and prepare supplier order drafts.

What you need to get started#

  • Access to "Inventory" → "Forecast" (/inventory?tab=forecast) and a selected warehouse.
  • Completed recipe cards and up-to-date stock.
  • Sales history of at least three of the same weekday, or seeding from a similar venue.
  • Defrost hours on product cards — for the defrost list.

The "Prep for a date" block works from placed orders and does not need sales history. Items without recipe cards are listed separately: the ingredient calculation for them is incomplete.

“Runs out around 19:00”#

For "Today", the "Will run out before the day ends" block shows items at risk of running short. If there is no risk or "Tomorrow" is selected, the block is not shown.

  1. Check the products and the estimated time stock runs out.
  2. Look at the "today’s pace ×…" label, if there is one.
  3. Decide what you can produce more of, buy more of or take off sale for a while.

The pace adjusts the remaining demand by today's sales deductions. Spoilage and staff meals are not included. The adjustment is limited to ×0.5…×2. If the pace was not measured, the usual profile is used. The exact hour is an estimate; sometimes the screen shows only "not enough for the rest of the day".

Prep plan#

  1. Select "Today" or "Tomorrow".
  2. Check the rows of the "Prep plan".
  3. If needed, change the quantity in the "To produce" column. Zero removes the item from the task.
  4. Click "Print" for a paper sheet or "Send to shift board" for a shared task with subtasks.
Column What it means
Product name The semi-finished item to prepare
"In Stock" Its current stock
"Needed" Demand from the forecast
"To produce" The missing quantity; you can change it
"By" Start of the daypart when stock stops covering demand; nested prep items may have no deadline

The composition is expanded down to five levels of nested semi-finished items. Prep stock is subtracted once. The printed sheet contains "Ingredients for the batch" and a "Done" field. Sending the plan again for the same date does not create a duplicate task.

When a prep item is ready:

  1. Click "Record output" in its row.
  2. Check the actual quantity in the production window that opens.
  3. Complete the document following the production instructions.

Marking a task done on the task board does not post a stock production by itself.

Prep for a date from placed orders#

Use this block for orders with a set time: pickup, delivery or serving at a table.

  1. Go to "Prep for a date".
  2. Choose a date; tomorrow is set by default.
  3. Check the prep sections.
  4. Click "Print".
Section What to check
"By station" Dishes and ingredients by KDS station; semi-finished items are marked "semi-finished"
"Raw goods in total" Total demand with semi-finished items broken down, without subtracting stock
"Notes" Item requests and order comments
"By table" Serving time, guest name, cutlery, items and comments

The venue's open orders with a serving time on the selected day are included, including pre-orders that are placed but not yet accepted by the operator. Cancelled and closed orders and unfinished carts are not included. Current orders without a serving time are not included either. A banquet needs such an order: a table booking or a calculation event alone does not create one.

The breakdown takes combos, add-ons and packaging by order type into account. Items without an assigned station may land in "No station".

Defrost list#

  1. Open the frozen product's card in "Inventory" → "Stock".
  2. In "Storage", choose "Freezer (−18 °C)".
  3. In the "Defrost time" field, enter the number of hours needed.
  4. Save the card.
  5. On the "Forecast" tab, choose the day and find the "Defrost list".
  6. Set "Kitchen starts at"; the initial value is 10:00.
  7. Check the quantity, start time and shortage warnings.
  8. Click "Print".

For example, if the kitchen starts tomorrow at 10:00 and defrosting takes 16 hours, you need to start today at 18:00. The kitchen start time is set in the list; it is not taken from the venue's schedule. The list does not create tasks on the shift board.

Supplier order draft#

  1. Find the "Purchase draft" block.
  2. Fill in "Cover, days": from 1 to 30, the initial value is 3.
  3. Check the demand, stock and the "On order" column.
  4. Uncheck the rows you do not need.
  5. Click "Generate orders".
  6. Open the created drafts in "Inventory" → "Procurement".
  7. Check the suppliers, quantities and prices before sending.

The calculation compares the forecast shortfall with the top-up to the target stock level and takes the larger value. If no target stock level is set, the reorder point is used. The selected day's demand is multiplied by the number of coverage days; this is not a sum of separate forecasts for each future day.

Quantities not yet received on this warehouse's open orders are subtracted from the recommendation: even drafts not yet sent to the supplier. The reorder quantity is then rounded up to the pack size. Close or cancel an old order you no longer need first, according to its status, so it does not reduce the new recommendation.

A separate draft is created for each supplier; rows without an assigned active supplier need one to be chosen. Orders are not sent automatically. Semi-finished items from the forecast are prepared, not bought as raw goods.

Limitations#

  • Events in the weekly revenue forecast do not increase the production plan automatically.
  • "Prep for a date" counts gross demand by current compositions, without subtracting stock and without future recipe versions.
  • The run-out time and the production plan depend on how complete the recipe cards are and how up to date the stock is.
  • The forecast applies to the venue, while stock and supplier orders apply to the selected warehouse.

Troubleshooting#

Problem What to do
Printing does not open Allow pop-ups for the admin panel and print again
No defrost block Check that at least one active product has defrost hours
The defrost block is there but has no rows On the selected day, the forecast does not need any products with defrost hours
All dishes ended up in "No station" Check how categories are assigned to stations in the KDS settings
The purchase recommendation is lower than expected Check "On order", including unsent drafts

FAQ#

Does the purchase draft go to the supplier right away?#

No. First check it in "Procurement" and send it separately.

Can I work without accumulated history?#

Yes, with orders for a selected date. The statistical prep plan needs history or seeding from a similar venue.

Was this article helpful?